01. What are the criteria of the ultra-high type of movable partition?
1、What kind of movable partition can be called ultra-high movable partition?
The extra-high type (elevation 9m-15m) can be called super-high partition, which is a common movable partition wall system used in many high star hotels. The extra-high partition can play an effective role in dividing the space of banquet hall and conference center, so that one hall can be used for multiple purposes without interfering with each other.
2、Here we share a case with you.
Hainan International Convention and Exhibition Center activity partition, Hainan International Convention and Exhibition Center, is currently the higher activity partition, height 15m, using an area of 4268m².


So what is the difference between this kind of partition and the rail type partition we usually see installed in the hotel? Usually we see the kind of hotel activity partition for 100 type activity partition, partition thickness of 100mm, the highest of this partition up to 12m.
And in Hainan International Convention and Exhibition Center used a solid movable partition German 100 type automatic turning system of ultra-high partition wall, this project in the door panel up to 15 m (we a solid partition can do 20 m high), the use of all-steel frame structure, the internal bottom load-bearing spiral telescopic structure, the use of automatic turning system and silent pulley, safety and maintenance is relatively easy. Configured with automatic turning system, with professional guiding block inside the guide rail.
When the movable partition is pushed to the turning or stacking place, the guiding block will automatically guide the partition door to glide to the designated track, and the gravity transfer system of strong clamp can ensure that each door panel will act more than 70% of gravity on the ground after fixed landing, which effectively reduces the load of the top steel frame and track, solves the stability problem and improves the durability of the partition.
02. What are the points to note in the installation of super high type partition?
1. Construction points of attention.
(1) observe the overall construction environment of the movable partition, carefully observe the surrounding environment to now survey the construction environment is the primary work, the main purpose of surveying the construction environment of the partition to be installed is to determine the site with or without installation conditions, fine record the location of the roof beams and columns and reserved space location, as well as the location of the air conditioning duct system, etc. to customize the final construction plan.
(2) can be based on the measurement, positioning according to the requirements of the construction drawings, in the indoor ground to put out the location control line of the movable partition, and the partition wall location line to the side wall and the top plate; and then the line should be populated with the installation location line of the fixed parts; the installation height of the track must be discussed with the installation of the ceiling construction team, otherwise it will breed a lot of unnecessary trouble.
(3) steel structure and track fixings installation steel structure is a load-bearing structure connecting the ceiling top with the track, steel structure involves the safety of the whole movable partition system, the designer needs to focus on; through the calculation of the weight of the movable partition wall, determine the load borne by the track and the specifications of the pre-buried parts, the way of fixing, etc., and then select the track and other fixings according to the design requirements.
2、Construction process.
1)Installation of track
Suspended track: The suspension-oriented fixing method is to install the pulley on the top surface of the partition and connect it with the upper suspended track. Track, pulley should be selected according to the size of the load-bearing weight. Light movable partition wall, track with wood screws or screwing screws fixed in the wooden frame or steel frame along the top. Heavy movable partition wall, the track is fixed on the steel skeleton with butt screw or welding.
Support track: support oriented fixed way is pulley in the lower part of the partition, and the ground track constitute the lower support point. The track is fixed with expansion bolts or with track pre-built parts, and the guide rail is installed along the top wooden frame.
Installation of the track: should be installed in advance according to the specific circumstances of the track, the pulley or track reserved opening (generally in the 1/2 partition against the wall).
2)Installation of movable panels
According to the installation mode, accurately draw the pulley placement line on each panel, then fix the fixed frame of the pulley with screws on the upper stile or lower stile of the partition fan; then install the panel into the track piece by piece, adjust each panel perpendicular to the ground, and push and pull the flexible rotation, and finally carry out the connection of each fan fixed, usually between adjacent panels with hinges connected.
3)Finish
According to the requirements of the hotel interior design for finish decoration, generally using soft package, framed cold mounted solid wood panels, paste decorative panels, set glass, etc.; finish done before the paint finish or edge, finish decoration construction according to the corresponding two-quota requirements, do the hotel style finish selection.
4) Commissioning.
After the installation of movable panels, the panel height, sealing and other details to debug, after debugging clean up the site, complete the installation work.